What is a quantity take-off in construction?
What a take-off includes
- Item: what is measured, such as “stud partition type A”.
- Quantity and unit: 46.0 m, 119.6 m², 24 nr.
- Where it came from: drawing number and revision.
- How it was got: from a written dimension, scaled, counted or assumed.
Take-off vs estimate
A take-off is quantities only. An estimate puts rates against those quantities to reach a price. Keeping them separate means you can re-price quickly when rates change, or re-measure quickly when the drawings change.
Material take-off
A material take-off (MTO) goes one step further and converts quantities into materials: boards, bricks, cartridges, tiles. Our trade guides show how, for example plasterboard and sealant.
Manual, digital and AI take-off
Take-offs used to be done with a scale rule on paper. Most are now done on screen with PDF measuring tools, and AI tools such as QuantRead can now do the first pass automatically.