Step 1: count and size the openings
Use the window and door schedule if there is one; otherwise read written dimensions on the elevations. Note which sizes you had to scale and which you had to assume.
Step 2: work out the perimeters
- Windows: 2 × (width + height) per opening.
- Doors: usually sides and head only, height + height + width.
- Movement joints: measure each vertical and horizontal run.
- Panel joints: measure each joint between cladding or spandrel panels.
- Internal beads: only if the specification calls for them.
Step 3: metres per cartridge
Multiply the joint width by its depth to get the cross-section. A 10 × 10 mm joint is 100 mm², and 100 mm² × 1,000 mm = 100,000 mm³, which is 100 ml per metre. Divide the cartridge size by that figure to get metres per cartridge.
| Joint (width × depth) | ml per metre | Metres per 310 ml | Metres per 380 ml |
|---|---|---|---|
| 6 × 6 mm | 36 | 8.6 | 10.6 |
| 10 × 10 mm | 100 | 3.1 | 3.8 |
| 15 × 10 mm | 150 | 2.1 | 2.5 |
| 20 × 10 mm | 200 | 1.6 | 1.9 |
| 25 × 12 mm | 300 | 1.0 | 1.3 |
Step 4: add waste in your price
Joints on site are rarely the exact size drawn, and you lose some in each cartridge. Allow for this in your price based on your own experience, rather than inflating the measure.
A worked example
24 windows at 1.2 × 1.5 m give 24 × 2 × 2.7 = 129.6 m. Three doors at 1.0 × 2.1 m, sides and head, give 3 × 5.2 = 15.6 m. Total 145.2 m. At 10 × 10 mm that is 145.2 ÷ 3.1 = 46.8, so 47 cartridges before waste.