What is a bill of quantities?
What is in a BoQ
- Preliminaries: site set-up, management, welfare and similar costs
- Measured work: each item with a description, unit and quantity, grouped by work section
- Provisional sums for work that cannot yet be measured
- Dayworks and a summary that carries each section total through
NRM2 and SMM7
NRM2 is the RICS New Rules of Measurement for detailed measurement of building works. It replaced SMM7 (the Standard Method of Measurement, 7th edition) as the UK standard. It sets out what to measure, how, and how to describe it, so bills from different surveyors can be priced the same way.
BoQ vs take-off vs bill of materials
| Document | What it is | Who uses it |
|---|---|---|
| Quantity take-off | The raw measured quantities from drawings | Estimators, QSs, trades |
| Bill of quantities | Quantities written up to a standard with full descriptions, for tender pricing | Clients, QSs, tendering contractors |
| Bill of materials | The materials needed to build, such as boards, bricks and cartridges | Buyers and site teams |
Read more in What is a quantity take-off?.
Where software helps
Writing the bill is skilled work. Measuring the quantities behind it is the slow part. QuantRead does that measuring and exports CSV you can build your BoQ from. It does not write NRM2 descriptions. See bill of quantities software.