Short answer: Read the revision box and look for revision clouds first, then check the drawing register for which sheets were reissued. For anything not clouded, overlay the old and new PDFs or compare your quantities line by line. A change in a total is the quickest way to see where the design moved.

Revision box and clouds

Each reissue should add a line to the revision box with a letter or number, a date and a short description. Changed areas are often marked with a revision cloud and a triangle tag. They are useful, but not every change gets clouded.

The drawing register

The register or issue sheet lists every drawing and its current revision. Compare it with what you priced from to see which sheets changed.

Overlay the PDFs

Many PDF tools can overlay or compare two versions and highlight differences in colour. It works best when both versions are vector PDFs at the same size.

Compare the quantities

ItemRev BRev CChange
Partition (m)146158+12
Doors (nr)2426+2
Ceiling (m²)4104100

Running both revisions through a take-off and comparing totals shows where the design moved, even when the change was not clouded. With QuantRead you can run each revision as its own job and compare the lines.

Why it matters

Changes after you priced are potential variations. Keep a record of which revision you priced from, and raise changes promptly.

Tags: drawing revisions, variations, estimating

Let QuantRead do the measuring

Upload a PDF, pick your trade, and get an editable take-off with the scale used and a check-on-site list.

Try it free – 1 drawing, up to 3 pagesSee pricing

Related posts

All posts · FAQ · Take-off by trade

How do you check what changed between drawing revisions? | QuantRead