How do you read construction drawings?
Start with the title block
The box in the corner tells you the project, the drawing number, the revision letter or number, the scale (for example 1:50 @ A1), who drew it and the date. Check the revision against the drawing register or the latest issue sheet before you take anything off it.
Know which view you are looking at
| Drawing | What it shows | What you take off it |
|---|---|---|
| Plan | The building from above, cut at about 1 m | Room sizes, wall lengths, doors, floor areas |
| Elevation | One face of the building | Windows, facade areas, heights |
| Section | A slice through the building | Floor-to-ceiling heights, build-ups, roof pitch |
| Detail | A junction at large scale | How things fit together, specific products |
| Schedule | A table, not a drawing | Window, door and finish types and sizes |
Read the legend and the notes
Symbols for sockets, lights, fire doors and drainage vary between practices, so always read the legend. Notes on the drawing often carry information that is not drawn, such as “all partitions to be 100 mm stud unless noted”.
Dimensions beat scaling
Use the written dimensions wherever there are any. If you must scale, check the scale first against a written dimension, as explained in How do you scale a PDF drawing to measure it?. Many drawings carry a note saying “do not scale”, which means the designer will not stand behind a scaled figure.
Cross-check between sheets
A window on the elevation should appear on the plan and in the schedule with the same size. If they disagree, raise a query rather than guessing: that is how missed items and extras are avoided.
Getting the numbers out
Once you can read the drawings, the take-off is the next step: see How do I do a take-off from PDF drawings?. QuantRead reads the title block and measures for your trade, but it is still worth knowing how to check what it found.
Tags: reading drawings, title block, scale