Costs and pricing

How do subcontractors price a tender from drawings?

Short answer: Read the enquiry and scope first, find every drawing that shows your work, take off the quantities for your trade, then build rates from labour, materials and plant. Add waste, access, prelims and overheads, list your assumptions and exclusions, and check the return date and contract terms before you send it.

1. Read the enquiry properly

Check the scope of works, the specification, the programme, payment terms and any amendments to the subcontract. Many problems later come from scope that was in the enquiry but not in the price.

2. Find your work on the drawings

Your package may be spread across plans, elevations, sections and details. List the sheets that show it, and note anything shown only in the specification.

3. Take off the quantities

Measure in your trade’s units and keep the working. Our take-off guide covers the method, and QuantRead for subcontractors gives you a first pass for your trade.

4. Build the rates

ElementAsk yourself
LabourHow many metres or square metres a day, with how many people?
MaterialsUnit cost, plus waste and cuts
Plant and accessScaffold, MEWP, towers: whose is it?
PrelimsTravel, parking, welfare, supervision
Overheads and profitYour percentage, set before you look at the total

5. Assumptions and exclusions

Write down what you assumed, such as working hours, access or who supplies what, and what you have excluded. It protects you if the drawings change.

6. Check before you send

Re-check the biggest lines, the drawing revisions you priced from and the return date. Keep a copy of everything you priced from.

Tags: subcontractors, tendering, pricing

Let QuantRead do the measuring

Upload a PDF, pick your trade, and get an editable take-off with the scale used and a check-on-site list.

Try it free – 1 drawing, up to 3 pagesSee pricing