How do subcontractors price a tender from drawings?
1. Read the enquiry properly
Check the scope of works, the specification, the programme, payment terms and any amendments to the subcontract. Many problems later come from scope that was in the enquiry but not in the price.
2. Find your work on the drawings
Your package may be spread across plans, elevations, sections and details. List the sheets that show it, and note anything shown only in the specification.
3. Take off the quantities
Measure in your trade’s units and keep the working. Our take-off guide covers the method, and QuantRead for subcontractors gives you a first pass for your trade.
4. Build the rates
| Element | Ask yourself |
|---|---|
| Labour | How many metres or square metres a day, with how many people? |
| Materials | Unit cost, plus waste and cuts |
| Plant and access | Scaffold, MEWP, towers: whose is it? |
| Prelims | Travel, parking, welfare, supervision |
| Overheads and profit | Your percentage, set before you look at the total |
5. Assumptions and exclusions
Write down what you assumed, such as working hours, access or who supplies what, and what you have excluded. It protects you if the drawings change.
6. Check before you send
Re-check the biggest lines, the drawing revisions you priced from and the return date. Keep a copy of everything you priced from.
Tags: subcontractors, tendering, pricing